French nuclear regulator says China cooperation lacking

China is moving quickly to become the first country to operate the world’s most powerful atomic reactor even as France’s nuclear regulator says communication and cooperation on safety measures with its Chinese counterparts are lacking.

In the coastal city of Taishan, 100 miles (160 kilometers) from the financial hub of Hong Kong, Chinese builders are entering the final construction stages for two state-of-the-art European Pressurized Reactors. Each will produce about twice as much electricity as the average reactor worldwide.

France has a lot riding on a smooth roll out of China’s EPRs. The country is home to Areva SA (AREVA), which developed the next-generation reactor, and utility Electricite de France SA, which oversees the project. The two companies, controlled by the French state, need a safe, trouble-free debut in China to ensure a future for their biggest new product in a generation. And French authorities have not hidden their concerns.

“It’s not always easy to know what is happening at the Taishan site,” Stephane Pailler, head of international relations at France’s Autorite de Surete Nucleaire regulator, said in an interview. “We don’t have a regular relationship with the Chinese on EPR control like we have with the Finnish,” said Pailler referring to another EPR plant under construction in Finland.

Calls and faxes to China’s National Nuclear Safety Administration regulator seeking comment went unanswered. China General Nuclear Power Corp, the atomic operator that is building the reactor with the French, didn’t responded to queries.

First indications

The first indications of French unease came when Philippe Jamet, one of the regulator’s five governing commissioners, testified before French Parliament in February.

“Unfortunately, collaboration isn’t at a level we would wish it to be” with China, Jamet said. “One of the explanations for the difficulties in our relations is that the Chinese safety authorities lack means. They are overwhelmed.”

Then, in March, EDF’s internal safety inspector Jean Tandonnet published his annual report to the utility’s chief executive that detailed a mid-2013 visit to the Taishan building site.

He wrote that “the state of conservation” of large components like pumps and steam generators at Taishan “was not at an adequate level” and was “far” from the standards of the two other EPR plants, one in Finland and the other in Flamanville, France. Tandonnet urged corrective measures and wrote that studies “are under way on tsunami and flooding risks.”

Safety procedures

Tandonnet’s report notwithstanding, Herve Machenaud, EDF senior executive vice-president in charge of generation said EDF is satisfied with China’s safety procedures. In China, “there is real, independent control that works at least as well as in most countries,” Machenaud said.

Some 28 reactors of various models are currently under construction in China. That’s more building than any other nation on the planet, and the country hasn’t reported a serious nuclear accident in the 22 years it has operated nuclear plants for commercial use.

Still, the international nuclear industry and its regulators have remained skittish following the 2011 Fukushima meltdown in Japan. In that catastrophe, radiation spread well beyond Tokyo, 135 miles from the wrecked power plant, in a disaster that rallied regulators worldwide to be more vigilant.

And in a rare public comment about safety concerns, China’s own State Council Research Office three years ago warned that the development of the country’s power plants may be accelerating too quickly.

For the rest of the story, continue reading here.

Like this content? Join our growing community.

Your support helps to strengthen independent journalism, which is critically needed to guide business and policy development for positive impact. Unlock unlimited access to our content and members-only perks.

Terpopuler

Acara Unggulan

Publish your event
leaf background pattern

Transformasi Inovasi untuk Keberlanjutan Gabung dengan Ekosistem →