Plans for more power plants delayed or scrapped

The construction of 10 nuclear power plants and one tidal power plant scheduled to be completed between 2013 and 2027 has been either put off or canceled, plant operators said, fanning concerns about power shortages.

The 11 plants, if completed, altogether could have produced about 12.7 million kilowatts of electricity, which accounts for about 6.4 percent of the nation’s power supply.

“We have postponed or canceled some plant construction deals because the government has become more careful about giving out approval after the Fukushima nuclear disaster,” said an official of the Korea Hydro and Nuclear Power Co.

Nuclear plant Sinuljin-1 and Sinuljin-2, originally set to be completed in June 2016 and June 2017 respectively, had their completion date postponed by at least 10 months, after failing to obtain the government approval on time.

The completion date of Sinuljin-3, Sinuljin-4, Sinkori-5 and Sinkori-6 were postponed by one year for failing to obtain the state approval, and Sinkori-7 and Sinkori-8 construction projects were canceled as the company faced difficulties in securing land for the construction site.

The KHNP decided to put off Incheon tidal power plant by about three years to June, 2020, the officials said.

South Korea currently has 23 nuclear reactors in operation, supplying about 30 percent of its entire electricity consumption.

The country seeks to bring the number of reactors to 39 by 2030.

Like this content? Join our growing community.

Your support helps to strengthen independent journalism, which is critically needed to guide business and policy development for positive impact. Unlock unlimited access to our content and members-only perks.

最多人阅读

专题活动

Publish your event
leaf background pattern

改革创新,实现可持续性 加入Ecosystem →